ESIP Project Development Process
Completed
5/23/23
Energy Savings Plan Development
• Kick-Off Workshop, Baseline, ECM, and M&V Workshop
• Site Audits and Bid Solar PPA
• Client Charette
• Submit ESP to PSE&G, 3rd Party and BPU
• Execute Implementation Contract
Completed 8/31/23
Design & Bid Spec Development
• Financing
• Work with CHA on Design of ECMs
• Bid Specification Development
Completed 11/17/23
Procurement
• Advertise Bids
• Pre-Proposal Meetings & Site Visits
• RFI Process
• Public Opening of Bids
• Evaluation of Bids and Subcontractor Selection
Completed
4/30/25
Construction
• Pre-Construction Activities
• Installation
• Punch List Items/Commissioning/Training
• Project Close Out
Completed 4/30/26
Performance Period
• Measurement and Verification with Guarantee
• Field Measurements
• ECM Data Logging/Trending
• Utility Bill Analysis